Report of the Building Committee

December 29, 2002

In early 1998 Dora Coffey offered to give the church some General Electric stock if they would install an elevator with the gift.  She said she wanted to see the results of her gift and not wait until the gift was a part of her estate.  It was a challenge for the church to handle that kind of a building project, but right away the decision was made to put in a first class elevator and to keep the addition in harmony with the original building.

Jim Wilson of APA was hired as the architect.  From his association with building projects at the Crowell Home, several members knew of him and his work.  At the first meeting of the building committee and the architect, the project was outlined as having three main objectives:  (1) an improved stairway so that everyone--young, old, or handicapped-- would feel safe on the stairs, (2) a handicapped accessible rest room, and (3) an elevator.  The elevator would give access to all three levels of the church.

The architect when looking at the existing floor plan, surprised us by adding the condition that the pastor's study should be reached through a hallway which was on the same level as the sanctuary.  We had become so accustomed to going up and down stairs to get to that room that we had not noticed the inconvenience of all those steps.  So the floor plan was drawn and approved.  The windows that were to be removed would be reinstalled in the new addition.  There were three windows:  the restroom window, the window on the west wall of the south annex room, and one of the south windows in the pastor's office (formerly the Sunday School room upstairs).  One of those windows had stained glass and the other two did not.  Through another gift, a new stained glass window was added to the project.
Construction began in 1998 when we let a contract to Welchert Construction for the demolition.  Steve Peterson was the contractor for the concrete and the concrete block work.  Forman Brothers were the framing contractor.  They completed their work in the fall of 1998.  
Duane Matzen was the roofer, and the roof was done in red cedar shingles to conform to the requirements for an historic building on the National Register.  The contract for the elevator was given to Complete Access, who would install a Concord three-stop elevator.  The plumbing and heating contractor was Jack Brothers of Tekamah, and the electrician was Judt Electric.  The insulation, R-19 in the walls and R-25 in the ceilings, was installed by Cornhusker.  Dan Baker was the drywaller.  Finish carpentry was done by Ed Jipp and Hugh Shields, using millwork produced by S. E. Smith of Blair.  Bob Welsh repaired one of the original windows as well as producing the stained glass for the window on the west wall.  All of the handrails and special woodwork for the stairs were constructed by Paul Jipp.  Hugh Shields did the painting.  The ceramic tile work was done by Paul Jipp.  Northeastern was the suspended ceiling installer, and the carpet was installed by Nebraska Furniture Mart.

Brian Lunn worked with the drywall crew.  Lavern Schmidt worked with the clean-up crew, and Craig Schmidt helped with some of the ceiling insulation.  Further help was given by Ed and Darleen Ferris, John Stepanek, Ken Rhoades and Ken Beaty.  Shirley Schmidt, Shirley Jipp, Phyllis Shields, and Rose Ruzika were among those who furnished coffee, pie, and cookies.  

One of the special features of the building is that the elevator has three stops enabling access to all three floors.  This necessitates entrance to the car on two floors from the east and on the grade entrance floor from the west.  By state regulations, the elevator must have a phone line and a phone in case there is a mechanical failure and the passengers get stuck between floors.  It must also have certain safety devices on the doors and the way they open as well as a safety catch mechanism in case the car would begin to fall for any reason.  The elevator shaft and shaft ceiling must be fireproof as well as the equipment room.  The elevator is operated hydraulically with a pump and cylinder, but a cable and pulley system actually attaches to, and operates the car.

Other features of the renovation are that all the doors and woodwork are done in natural red oak.  The finish is provincial stain with two coats of satin polyurethane varnish.  The tile work is done in 12x12 ceramic tile in two colors and includes the outside walls of the elevator shaft.

The design of the addition was approved by the Fire Marshal after he ruled that the entire addition could be a contained area, shut off from the rest of the building by fire doors and two-hour fire-rated walls.  The alternative was to enclose the stairway in a fire rated enclosure with fire doors that must be closed at all times.  The storage area under the stairs was added later and is also totally fireproofed with a two-hour fire rating.
The ground was broken to commence construction on August 16, 1998, and the dedication service was November 7, 1999.  That service included dedication of the new stained glass window in honor of John Fritzmeier and the handrail in honor of Jeri Fritzmeier.

 